99. If, following the verification of the project plan or project report as the case may be, the verifier notes a failure to comply with a condition, the verifier must(1) in the case of a project plan, assess its impact on the eligibility of the project, the validity of the initial inventory and the characterization of the baseline scenario and determine if it leads to significant errors, omissions or inaccuracies;
(2) in the case of a project report and with respect to a condition relating to the quantification of GHG fluxes that cannot be corrected by the promoter, assess its impact on the GHG fluxes recorded in the project report and determine if its leads to significant errors, omissions or inaccuracies.
If the failure to comply with a condition relating to the quantification of GHG fluxes cannot be corrected by the promoter but does not lead to significant errors, omissions or inaccuracies, and if the verifier concludes that the other conditions of the Regulation have been met and that there are no significant errors, omissions or inaccuracies, the verifier gives the promoter a positive verification opinion.
2022-11-17M.O. 2022-11-17, s. 99.